All Residents, Central Heating, Communal Services, Hot Water, Major Works

Heating Works is expected to be completed by the start of September 2011

Heating Works is expected to be completed by the start of September 2011The Camden Council has informed us that the Major Heating Works will finish by the start of September 2011.

 

 

 

 

Please see all the latest updates below:


TIMELINE OF EVENTS AND UPDATES


On 09 August 2011 at 15:22 a resident wrote:
To: tonybowcut@theapollogroup.co.uk; Michael, Richard
Cc: HousingRepairsInbox
Subject: Heating Works on the Curnock Estate


Dear Mr Bowcut and Mr Michael,

The heating works were supposed to finished last January. Then it was postponed until the beginning of July 2011. We are in the middle of August and the works have not finished.

Could you please provide us with an update regarding the Heating Works?

Yours sincerely


On 09 August 2011 at 15:22 “Michael, Richard” <Richard.Michael@camden.gov.uk> wrote:


Dear Resident,

The first phase of the works was due to finish in January as you correctly state. This over-run due to the issues with incorrectly sized coils in the calorifiers and time it took to have the new ones made and imported from Portugal .

That phase of the works is now complete.

The second phase was the replacement of the hot water secondary pipework in the boiler house and garage areas ( Camden and Lomax).

The pipework is installed and the insulation is being finished at the moment. Changing over the risers connections from the old to the new is the final stage of the works and this is expected to be completed by the start of September.

Regards

Richard Michael
Mechanical Contract Manager

Telephone: 0207 974 2048